Employee Appreciation Day Spotlight: Tucson Crews Working on Sahuarita Supply Slip Liner
March 1, 2024
This Employee Appreciation Day, we want to acknowledge the teamwork and dedication of our crews working on the Sahuarita Supply Slip Liner project. Recently, the team was backfilling one of two massive Jack and Bore pits — each a staggering 60 ft long, 20 ft wide, and 40 ft deep. These pits are crucial for installing 210 LF of 48-inch steel casing that houses 30-inch Ductile Iron Pipe. Their hard work is the foundation of this important project for the City of Tucson. We are very proud of you all!