This National Public Works Week, B&F is proud to highlight that we’re officially one month into construction on the McKellips Road Relief Sewer Project for City of Mesa! 🚧👏
This CMAR includes the installation of 10,473 linear feet of sanitary sewer line, procurement and installation of 27 precast manholes, water line installation and realignment, CIPP lining, manhole rehabilitation, bypass operations, storm drain removal and installation, and gas installations. The project stretches from the intersection of N Brown Road and Stapley Drive to the intersection of N Gilbert Road and E McKellips Road.
Our crews have been working diligently and safely with stakeholders while keeping traffic disruptions to a minimum. Great work Janessa Murphy and Jaime! We are excited to continue construction on this project and look forward to updating you on our progress into next year.