Osborn Parallel Sewer

B&F initiated two GMP’s to expedite this project for Scottsdale due to an adjacent reconstruction project starting in early 2021. The project involved the placement of a new, larger sewer main and the development of a custom structure to divert flow off the line to another adjacent line for additional options. B&F worked with the Owner through design to move the alignment due to multiple utility impacts that would far exceed the cost of completing a standard remove and replace with a larger diameter pipe in the existing alignment under a short-term bypass. B&F also proposed a complete road improvement project coming shortly after the sewer project to eliminate the double T-top section of the pipe. These cost savings went 100% to the Owner.

B&F placed roughly 120 LF of 12-inch sewer line at 10-13 foot depth, 1,260 LF of 15-inch sewer main (down Osborn Road between 70th Street and Drinkwater) at 15-foot depth, and 1,185 LF of 18-inch sewer main (from Drinkwater to Miller on Osborn) at a 15-foot depth. The project also included a 42-inch steel casing Jack and Bore at 286 LF across Scottsdale Road, 14 each sewer lateral tie-ins, 180 LF of 6 to 8-inch waterline conversion from ACP to ductile iron pipe, flatwork, ADA ramps, pedestrian refuge construction, and 12 each Armorock manholes. B&F successfully completed the jack and bore on grade for the new sewer installation and adapted to unforeseen conditions without cost impacts to the owner. B&F also provided turnkey sewer bypass services for tie-in locations. B&F self-performed most of the work on this project, including all pipe installation, bypass and flow management, removals, shutdowns, and testing.

Owner

Service

Location

Market

Delivery Method

Completion Date

City of Phoenix
Wet Utilities
Scottsdale, AZ
Municipal
CMAR
2021

Owner

City of Phoenix

Services

Wet Utilities

Location

Scottsdale, AZ

Market

Municipal

Delivery Method

CMAR

Completation Date

2021

similar projects

;